User Manual‎ > ‎Projects‎ > ‎

Resource Calculation

 

How do I access the Resource Calculation screen?

1. Click on ¨Projects¨
2. Click on ¨Resource Calculation¨


What is the Resource Calculation screen for?

Through the resource calculation screen we can obtain and view all the resources included in the estimate, that will be necessary to execute the project.

The data can be filtered by resource type, or dragging the header in each column.

What does each field on the screen mean?

  • Global

On the resource calculation screen we can view in detail, and by type, all the resources needed for the execution of the selected project.

 

 
 Name  Description Field type
Unitary code Resource code  
Unitary description Resource description  
Unitary type Resource type  
Measurement unit Measurement unit  
Calculated units Unitaries planned for use  
Cost price Cost price  
Total cost Total cost   
  • Chapter

In BrickControl you can obtain a detailed view of all resources per chapter. 
 
 Name  Description  Field type
Chapter code Chapter code  
Unitary code Resource code  
Unitary description Resource description  
Unitary type Resource type  
Measurement units Measurement units  
Calculated units Unitaries planned for use  
Cost price Cost price  
Total cost Total cost   
  • Work units 

In BrickControl you can obtain a detailed view of all resources per chapter and per work unit.
 
 
 Name  Description  Tipo de Campo
Chapter code Chapter code  
Work unit code                   Work unit code  
Contract code Contract code  
Unitary code Resource code  
Unitary description Resource description  
Unitary type Resource type   
Measurement unit Measurement unit  
Calculated units Units planned for use  
Cost price Cost price  
Total cost Total cost   
 

How to´s

  • How do I get a resource calculation by resource type?

1. Click on ¨Projects¨

2. Click on ¨Resource Calculation¨

3. Select the resource type

4. Select Global, Chapter or Work Unit

5. Click on ¨Open¨

6. Select the project

7. Now you can view the data on the Resource Calculation screen

  • How do I get a Global resource calculation?

1. Click on ¨Projects¨

2. Click on ¨Resource Calculation¨

3. Select the resource type

4. Select Global

5. Click on ¨Open¨

6. Select the project

7. Now you can view the data on the Resource Calculation screen

  •  How do I get a resource calculation by chapter?

1. Click on ¨Projects¨

2. Click on ¨Resource Calculation¨

3. Select the resource type

4. Select Chapter

5. Click on ¨Open¨

6. Select the project

7. Now you can view the data per chapter on the Resource Calculation screen

 
  • How do I get a resource calculation by work unit?

1. Click on ¨Projects¨

2. Click on ¨Resource Calculation¨

3. Select the resource type

4. Select Work unit

5. Click on ¨Open¨

6. Select the project

7. Now you can view the data per work unit on the Resource Calculation screen

  • How do I modify a resource´s price?

1.Click on ¨Projects¨

2. Click on ¨Resource Calculation¨

3. Select the resource type

4. Select Global, Chapter, or Work unit

5. Click on ¨Open¨

6. Select the project

7. Click in the field you want to modify in the price column 
8. Modify the data as needed
 

Where can I use resource calculations

Resource calculations are used on Purchase management.